|
Over the anticipated six-year construction period of the Wuskwatim project, WPLP will be posting information about the project including progress reports and news materials.
Access to relevant information prior to the June 2006 project approval and commencement of construction is also available.
Check the links to find specific information you're looking for.
Background Information
Construction of the Wuskwatim Project commenced in August 2006. If you want pre-construction information please refer to the Nisichawayasihk Cree Nation's website, which has comprehensive information on the negotiations leading up to the signing of the Wuskwatim Project Agreement, or Manitoba Hydro, which has comprehensive information on the environmental reports and other historical information on hydroelectric development in northern Manitoba.
Construction Videos

• Wuskwatim Construction Update 2008-2009 Video – CREE VERSION
(Size 40 MB)

• Wuskwatim Construction Update 2008-2009 Video (Size 40 MB)

• Wuskwatim Construction Update 2006-2008 Video (Size 17 MB)
• Wuskwatim Construction Update 2006-2008 Video - CREE VERSION
(Size 17 MB)

• Construction Activities August-October, 2008 Video (Size 4.2 MB)
Concrete Placement
As of June 17, 2010, there have been approximately 83,100 cubic metres
of concrete placed in all of the structures. This is approximately 70%
of the total quantity and consists of:
- Spillway –10,500 cubic metres. All concrete has been placed to
complete this structure.
- Service Bay – 16,300 cubic metres
- Intake – 16,100 cubic metres
- Powerhouse – 24,350 cubic metres
- Tailrace – 10,400 cubic metres
- Miscellaneous Structures – 5,450 cubic metres
The Service Bay and Powerhouse are enclosed to protect the overhead
crane and other sensitive operations from the elements. The temporary
enclosure over the Tailrace has been removed as the concrete has
progressed beyond the limits of the hoarding.
Turbine Generators
The installation of the Turbine Generators continues with the concrete
embedment of the Draft Tube Liner, and the installation of the Stay
Ring and Turbine Pit Liner in Unit 1. In Unit 3 the draft Tube Liner
has been assembled and aligned with the concrete embedment. The Unit
3 Stay Ring has been assembled on the Service Bay floor and will be
moved into place after the completion of the concrete works on the
Draft Tube Liner.
Stage II River Diversion
The River Management is currently in Stage I Diversion with the
Upstream Stage I Cofferdam diverting the water over Taskinigup Falls,
which allows the concrete structures to be constructed in the dry.
After the Spillway structure and gates are completed, the project will
be ready to start Stage II Diversion. In this process a Stage II
Cofferdam is constructed across Taskinigup Falls and a portion of the Stage I Upstream Cofferdam is removed to allow the entire flow of the
Burntwood River to pass through the Spillway. Once the water is
flowing through the Spillway the Main Dam can be constructed, in the
dry, behind the Stage II Cofferdam.
The preliminary work has started for the activities required for Stage
II River Diversion with the excavation of rock from the Spillway and
Intake Channels and the placement of fill materials for the Stage II
Upstream Powerhouse Cofferdam.
Powerhouse Crane
In November 2009, Phase 1 of the Powerhouse Crane installation was
competed in the Service Bay of the generating station. Phase 1 consisted
of lifting and assembling the main girder, auxiliary girder and trolley
on the crane rail some 35 ft above the service bay floor. This
installation took approximately four days to complete and at 275 metric
tons, put Wuskwatim atop of the list for the single largest overhead
crane in Manitoba Hydro's fleet.
Phase 2 installation and final commissioning of the Powerhouse Crane
started on March 1, 2010 and was completed by the end of March. The
overhead crane will play a key role in the construction of the
generating station and the installation of its three - 66 MW turbine
generators.
Construction Camp
The main construction camp is complete, including single-room bunkhouse
accommodation for over 700 workers. All support facilities are
operational, including the water treatment plant and sewage lagoon. The
completed Recreation Centre has free access for all workers to a
full-size gymnasium, racquetball courts, weight and exercise room, pool
tables, TV and internet rooms.
The camp area also has a chapel /
training facility, a restaurant / lounge and a sports field for baseball
and soccer. Hiking / cross-country ski trails are being developed. There
are cross-cultural training sessions, cultural ceremonies and counseling
services available to all employees. Most of the cultural activities
take place in the Cross Cultural Centre, which was completed in January
2009. All of the Cultural activities are managed and provided by NCN.
Wuskwatim Access Road
Approximately 2.2 million cubic metres of granular material has been
excavated and placed on the 48 km access road that runs from Provincial
Road 391 southward to the station site on the Burntwood River, 45 km
southwest of Thompson. The road provides year-round, all-weather access
to the construction site and year round maintenance is provided.
Structures Excavation
Excavation for the principal structures commenced in December 2007 and
was completed in February 2009. The work was done in two phases. Phase 1
in winter 2007 / spring 2008 included the removal of approximately
650,000 cubic metres of overlying soil and bedrock. Phase 2 had a
further 525,000 cubic metres of bedrock removed during the summer and
winter of 2008 from the areas of the principal structures and channels.
Total excavations to date are approximately 1,178,000 cubic metres of
overlying soil and bedrock materials. In parallel with excavation, the
construction of stage 1 upstream and downstream cofferdams were
completed.
Transmission Project
Construction of the transmission line from Birchtree to Wuskwatim has
been completed. Construction of the transmission lines from Wuskwatim to
Herblet Lake and clearing of right-of-way for the transmission line from
Herblet Lake to Ralls Island was completed in March. Line construction
is underway and will take place over two winter seasons, and finish by
April 2011. Design and material procurement has commenced for the
collector lines from the Wuskwatim Generating Station to Wuskwatim
Switching Station.
The control buildings at Birchtree and Wuskwatim switching stations have
been installed. Installation of electrical apparatus is underway at
Thompson Birchtree Station, Wuskwatim Switching Station, Herblet Lake
Station and Ralls Island Station. This work is expected to be completed
by summer of 2010. The transmission project is on schedule and will be
completed by summer of 2011.
Current Employment Statistics
As at End of May 2010
- 968 project employees
- Approximately 26 percent Aboriginal
Current project employees represent
those actively working at site, on rotational leave from site, and
currently on hiring recall as per Article 12.4.2 of the BNA.
For more employment detail please click here
|